The magnetic balance test of a transformer is a critical diagnostic procedure performed exclusively on three-phase transformers to verify the proper distribution of magnetic flux through the transformer core. This test is essential for detecting magnetic imbalances, inter-turn faults, core defects, and manufacturing defects that could lead to transformer failure. The magnetic balance test serves as a proactive maintenance tool during transformer commissioning, factory testing, and routine maintenance operations.
What is Magnetic Balance Test?
The magnetic balance test is a low-voltage electrical test performed on three-phase transformers to assess the uniform distribution of magnetic flux through the three-limb transformer core. The test is based on Faraday’s law of electromagnetic induction, which states that when voltage is applied to one phase winding, voltages are induced in the other two phase windings. The relationship between these induced voltages indicates whether the magnetic circuit is balanced or if defects exist.
Fundamental Principle
A three-phase transformer core typically has three vertical limbs arranged side by side:
- Left limb (carries winding of phase R/A)
- Middle limb (carries winding of phase Y/B)
- Right limb (carries winding of phase B/C)
When single-phase voltage is applied across one limb and its neutral, magnetic flux is induced through that limb. Due to the symmetrical arrangement of the three-limb core, this flux distributes through the other two limbs with different reluctance paths. The induced voltages in these limbs depend on the flux distribution and the transformer’s core geometry.
For a magnetically balanced transformer, the sum of induced voltages on the two remaining phases should equal the applied voltage:
\(V_{Applied}=V_{Induced\,Phase 1}+V_{Induced\, Phase 2}\)
This relationship confirms that the magnetic flux distribution is symmetrical and the core is healthy.
Why Magnetic Balance Test is Important
1. Detection of Inter-Turn Faults
Inter-turn faults are short circuits between consecutive turns of the same winding. These faults:
- Cause localized heating in the defective region
- Create circulating currents within the shorted turns
- Gradually propagate to adjacent turns, leading to catastrophic failure
- May not be detected by other electrical tests until severe damage occurs
The magnetic balance test can identify inter-turn faults early in the manufacturing process or during commissioning, preventing failures in the field.
2. Detection of Core Defects
The test detects various core abnormalities:
- Loose core joints between laminations, which increase reluctance
- Core shifting from design position, causing unbalanced flux paths
- Lamination insulation breakdown, causing eddy current losses
- Mechanical damage from transportation or handling
- Core saturation from improper design or damage
3. Verification of Uniform Flux Distribution
A properly designed transformer core allows equal reluctance paths for flux through all three limbs. The magnetic balance test verifies that:
- Flux distributes symmetrically through the core
- No mechanical or electrical defects disrupt flux paths
- The core is structurally sound and meets design specifications
Core Structure and Flux Distribution
Three-Limb Transformer Core Architecture

A standard three-phase transformer has a three-limb core with the following characteristics:
| Component | Description |
|---|---|
| Left Limb | Carries R/A-phase winding, outer limb position |
| Middle Limb | Carries Y/B-phase winding, central position |
| Right Limb | Carries B/C-phase winding, outer limb position |
| Top Yoke | Connects top ends of all three limbs |
| Bottom Yoke | Connects bottom ends of all three limbs |
Flux Distribution Pattern of Three Phase Transformer

When voltage is applied to one phase:
When R-phase is excited (230V applied between R and N) as per IEC 60076:
- Flux through R limb (left): 100% – Maximum flux through the excited limb
- Flux through Y limb (middle): 60-90% – Moderate flux through adjacent limb with closer reluctance path
- Flux through B limb (right): 10-40% – Minimum flux through far limb with longer reluctance path
The percentage distribution occurs because:
- The middle limb is closer to the excited limb, providing a shorter reluctance path
- The right limb is farther away, requiring flux to travel through longer paths in the yoke
- This creates asymmetrical flux distribution proportional to reluctance
When Y-phase (middle) is excited (230V applied between Y and N):
- Flux through Y limb (middle): 100% – Maximum flux
- Flux through R limb (left): 50% – Equal distance, similar reluctance
- Flux through B limb (right): 50% – Equal distance, similar reluctance
The middle limb shows equal distribution to outer limbs because it is equidistant from both.
Equipment and Apparatus Required for Magnetic Balance Test
| Equipment | Specification | Purpose | Quantity |
|---|---|---|---|
| Single Phase AC Supply | 230V, 50Hz (or 60Hz) | Applied test voltage | 1 |
| Autotransformer/Dimmer Stat | 0-250V, 20A rated | Voltage control for safe testing | 1 |
| Digital Multimeter | 0-100V AC | Measure voltages | 1 |
| Connecting Wires | Insulated PVC, min. 2.5mm² | Circuit connections | As needed |
| Safety Equipment | Gloves, goggles, insulated mat | Personal protection | 1 set |
| Grounding Cable | Properly rated earth wire | Safety grounding | 1 |
Step-by-Step Magnetic Balance Test Procedure
Step 1: Visual Inspection
- Check for visible damage, oil leakage, or loose components
- Document ambient temperature, humidity, and test location
- Record transformer serial number and previous test results if available
- Verify this is a three-phase transformer (magnetic balance test applies only to three-phase units)
Step 2: De-energization and Isolation
- Ensure the transformer is completely de-energized from all power sources
- Open and lock all applicable circuit breakers and disconnect switches
- Use a voltage tester to verify that zero voltage is present on all terminals
- Wait at least 5 minutes after de-energization to allow residual charge to dissipate
- Do not begin testing until zero voltage is confirmed on all terminals
Step 3: Disconnect Transformer Neutral from Ground
- Locate the transformer neutral point (star point for star-connected windings)
- Disconnect the neutral connection from ground or earth – this is crucial for accurate test results
Why disconnect neutral? If the neutral point remains grounded, the ground provides an alternate current path that bypasses the windings, causing inaccurate voltage measurements. Disconnecting the neutral ensures all magnetic flux flows through the intended limbs.
Step 4: Set Tap Changer to Nominal Position
- If the transformer has an on-load tap changer (OLTC) or off-circuit tap changer (OFCT), set it to the normal or nominal tap position
- Document the tap position used for testing
- Keep the tap in the same position for all three phases to ensure consistency
- Note: For autotransformers, the test should be repeated for both HV and IV windings
Step 5: Position Test Equipment
- Place the autotransformer/dimmer stat to ZERO position before any connections
- Arrange voltmeters and connecting wires in an organized, easily readable layout
- Ensure all test equipment is grounded properly for safety
- Verify all connections are tight and properly insulated
Step 6: Apply Single-Phase Voltage to First Phase (R-Phase)

Circuit Connection Setup:
- Connect positive terminal of autotransformer to the R-phase terminal (high voltage winding)
- Connect negative terminal of autotransformer to the neutral terminal of the transformer
- Prepare to measure:
- V1: Voltage applied between R and N (applied voltage)
- V2: Induced voltage between Y and N (induced in middle phase)
- V3: Induced voltage between B and N (induced in third phase)
Voltage Application Procedure:
- Check that all connections are correct before energizing
- Slowly increase the autotransformer voltage from ZERO to approximately 100-120V
- Allow the voltage to stabilize for 30-60 seconds before taking readings
Record Observations:
- Note V1 (applied voltage): __________ V
- Note V2 (induced at Y-phase): __________ V
- Note V3 (induced at B-phase): __________ V
Verification Calculation:
- Calculate: V1 = V2 + V3 (within ±5% tolerance is acceptable)
- Example: If V1 = 100V, V2 = 65V, V3 = 35V, then 100 ≈ 65 + 35 ✓ (Magnetically balanced)
- Document result: Balanced or Unbalanced along with calculated values
Step 7: Apply Single-Phase Voltage to Second Phase (Y-Phase)

Circuit Connection Modification:
- Reduce autotransformer voltage to ZERO and wait 10 seconds
- Disconnect the R-phase wire from the autotransformer
- Connect the Y-phase terminal to the positive terminal of autotransformer
- Keep the negative terminal connected to neutral
Voltage Application and Measurement:
- Increase voltage slowly from ZERO to 100-120V
- Allow voltage to stabilize for 30-60 seconds
- Measure and record:
- V1′ (applied voltage Y-N): __________ V
- V2′ (induced at R-phase): __________ V
- V3′ (induced at B-phase): __________ V
Verification Calculation:
- Calculate: V1′ = V2′ + V3′ (within ±5% tolerance)
- Example: If V1′ = 100V, V2′ = 50V, V3′ = 50V, then 100 = 50 + 50 ✓
- Document result: Balanced or Unbalanced
Step 8: Apply Single-Phase Voltage to Third Phase (B-Phase)

Circuit Connection Modification:
- Reduce autotransformer voltage to ZERO and wait 10 seconds
- Disconnect the Y-phase wire
- Connect the B-phase terminal to autotransformer positive terminal
- Keep neutral connection unchanged
Voltage Application and Measurement:
- Close autotransformer circuit breaker gradually
- Increase voltage slowly from ZERO to 100-120V
- Allow voltage to stabilize for 30-60 seconds
- Measure and record:
- V1” (applied voltage B-N): __________ V
- V2” (induced at R-phase): __________ V
- V3” (induced at Y-phase): __________ V
Verification Calculation:
- Calculate: V1” = V2” + V3” (within ±5% tolerance)
- Example: If V1” = 100V, V2” = 35V, V3” = 65V, then 100 ≈ 35 + 65 ✓
- Document result: Balanced or Unbalanced
Step 9: Repeat Test for Secondary Winding (if Applicable)



For autotransformers and certain transformer configurations:
- If the transformer has an intermediate voltage (IV) winding, repeat the entire procedure for that winding
- Apply single-phase voltage to each IV terminal
- Measure induced voltages between other IV terminals
- Record results in a separate observation table
- Compare results with HV winding for consistency
Step 10: De-energize and Disconnect
- Gradually reduce the autotransformer voltage to ZERO
- Wait 10 seconds for residual charge to dissipate
- Verify voltage on transformer terminals returns to ZERO using a voltage tester
- Disconnect all test equipment and connecting wires carefully
Step 11: Restore Transformer Connections
- Reconnect the neutral point to ground or earth (reverse of Step 3)
- Ensure the connection is tight and properly torqued
Step 12: Document Results and Analysis
Observation Table Completion:
| Phase Excited | V_Applied (V) | V_Induced_1 (V) | V_Induced_2 (V) | Sum (V) | Difference % | Result |
|---|---|---|---|---|---|---|
| R | 100 | 65 | 35 | 100 | 0% | Balanced |
| Y | 100 | 50 | 50 | 100 | 0% | Balanced |
| B | 100 | 35 | 65 | 100 | 0% | Balanced |
Result Interpretation
Magnetically Balanced Result:
- All three phase tests show voltage sum equal to applied voltage (within ±5% tolerance)
- Voltage distribution percentages fall within expected ranges:
- Center phase excited: 50% distribution to each outer limb
- Outer phase excited: 60-90% to middle limb, 10-40% to far limb
- No inter-turn faults detected
- Core structure is intact and symmetrical
- Transformer is PASSED ✓
Magnetically Unbalanced Result:
- Voltage sum deviates significantly from applied voltage (>5% deviation)
- Voltage distribution percentages are abnormal or inconsistent between phases
- Examples of unbalanced results:
- V1 = 100V, V2 = 40V, V3 = 50V → Sum = 90V (10% deviation – FAILED)
- V1 = 100V, V2 = 30V, V3 = 60V → Sum = 90V (FAILED)
- Indicates possible faults requiring further investigation
- Transformer is FAILED or requires additional testing
Conclusion and Recommendations:
If PASSED:
- “Transformer is magnetically balanced. No inter-turn faults or core defects detected.”
- “Core structure is intact with uniform flux distribution.”
- “Transformer is suitable for energization.”
If FAILED:
- “Magnetic imbalance detected. Further testing recommended.”
- “Possible inter-turn faults, loose core joints, or core shifting.”
- “Do not energize transformer. Consult manufacturer for investigation.”
- “Recommend SFRA test, winding resistance test, and visual core inspection.”
Acceptable Tolerance Limits
| Criterion | Acceptable Limit |
|---|---|
| When center phase is excited | Induced voltage in center phase: 50-90% of applied voltage. Induced voltages in outer phases: 30-70% of applied voltage. |
| When outer phase is excited | Induced voltage in adjacent middle phase: 60-90% of applied voltage. Induced voltage in opposite outer phase: 10-40% of applied voltage. |
| Voltage Sum Tolerance | Sum of two induced voltages: ±5% of applied voltage (i.e., if V_applied = 100V, sum should be 95-105V) |
| Phase Consistency | Results should be similar when test is repeated on the same phase |
| Zero or Negligible Voltages | Any phase showing zero or extremely low voltage (<5V when 100V applied) should be investigated for winding open circuits or loose connections |
Common Faults and Troubleshooting
Fault 1: Voltage Sum Significantly Less Than Applied Voltage
Example: V_applied = 100V, V_induced_1 = 30V, V_induced_2 = 40V, Sum = 70V (30% deviation)
Possible Causes:
- Inter-turn faults: Shorted turns create localized circuits that reduce voltage sharing
- Loose core joints: Laminations separating increases reluctance
- Core shifting: Physical displacement from design position alters flux paths
- Lamination insulation failure: Eddy currents bypass intended flux paths
Corrective Actions:
- Repeat test to confirm results
- Perform SFRA (Sweep Frequency Response Analysis) test for detailed core information
- Measure winding resistance to check for inter-turn faults
- Request visual core inspection by manufacturer
- Do NOT energize transformer until fault is resolved
Fault 2: Zero or Extremely Low Induced Voltage in One Phase
Example: V_applied = 100V (R phase), V_induced (Y phase) = 5V, V_induced (B phase) = 95V
Possible Causes:
- Open circuit winding: Complete break in one phase winding
- Loose terminal connection: Poor contact at terminal connection point
- Broken lead wire: Internal or external winding lead disconnected
- Severe core separation: Complete flux blockage between certain limbs
Corrective Actions:
- Check all terminal connections for tightness and corrosion
- Verify winding continuity using megohmmeter
- Perform winding resistance test on all phases
- Request manufacturer inspection for internal winding damage
- Mark transformer as “NOT SERVICEABLE” until repairs are completed
Fault 3: Abnormal Voltage Distribution Percentages
Example: When B phase (right limb) excited, V_induced (Y-middle) = 20% (should be 60-90%)
Possible Causes:
- Core asymmetry: Unequal limb sizes or cross-sections from manufacturing defect
- Partial core separation: Certain laminations or core sections loosely stacked
- Flux shunting paths: Metallic objects or unintended conductive paths bypass normal flux paths
- Design anomaly: Non-standard transformer construction (5-limb core, distributed windings, etc.)
Corrective Actions:
- Document exact percentage values and compare with manufacturer specifications
- Perform test at different tap positions to check consistency
- Compare results with baseline measurements if available
- Contact manufacturer with detailed test results for interpretation
- Consider SFRA test if magnetic balance test is inconclusive
Fault 4: Inconsistent Results When Test Repeated on Same Phase
Example: First measurement V_sum = 98V, Second measurement V_sum = 75V
Possible Causes:
- Unstable AC supply voltage: Utility voltage fluctuations affect measurements
- Residual magnetization: Previous test left core magnetized
- Loose transformer position: Physical movement between tests
- Poor multimeter contacts: Unstable connections in test leads
- Temperature effects: Temperature drift affecting insulation resistance
Corrective Actions:
- Verify AC supply voltage is stable (use voltmeter on supply)
- Allow longer stabilization time (60-90 seconds) between tests
- Place transformer on stable foundation and check for movement
- Inspect test lead connections for corrosion or looseness
- Consider allowing 15-30 minutes between repeated tests for temperature stabilization
- Use same test voltages and tap positions for all repeated measurements
Fault 5: Asymmetrical Voltage Distribution Between Phases
Example:
- R phase excited: V_Y = 70%, V_B = 30% (expected: 60-90%, 10-40%) ✓
- Y phase excited: V_R = 55%, V_B = 45% (expected: 50%, 50%) – Slightly skewed
- B phase excited: V_Y = 65%, V_R = 35% (expected: 60-90%, 10-40%) – Possible core defect
Possible Causes:
- Loose laminations: Core joints separating unevenly
- Core layer misalignment: Laminations stacked at angles
- Winding displacement: Phase windings shifted from design position
- Manufacturing defect: Core assembly quality issue from factory
Corrective Actions:
- Review all test measurements carefully for recording errors
- Consult manufacturer’s baseline measurements if available
- Perform detailed SFRA analysis for frequency-dependent behavior
- Request non-destructive inspection (thermal imaging, ultrasound)
- Consider partial core disassembly by authorized service center for inspection
Conclusion
The magnetic balance test of a transformer is an essential diagnostic procedure for three-phase transformers that detects inter-turn faults, core defects, and magnetic imbalances that could lead to transformer failure. By applying single-phase voltage to each winding and measuring induced voltages, this test verifies uniform flux distribution through the transformer core based on Faraday’s law of electromagnetic induction.